Impact of the Fukushima Prefecture offshore Earthquake on our business activities (2nd UPDATE)
Information listed here is shown as of the date of release. Please note that production, sales and programs may be terminated or contents such as specifications and prices may be modified by the time you read this information.
Feb 18, 2021
The impact of the Fukushima Prefecture offshore Earthquake that occurred on February 13 on our business activities is as follows.
There was damage to equipment at some production bases. Restoration work is underway.
Alps Alpine Co., Ltd. Wakuya Plant
Some restorations were needed due to
damage on the water pipes. The operations were temporarily stopped but have
since resumed.
Alps Alpine Co., Ltd. Taira Plant
Due to damage on the pure water
generator, pure water could not be supplied to the line. The operations were
partially stopped and restoration work is in progress.
All operations
are scheduled to resume on February 23rd.
The scheduled restart date has been postponed, but there will be no impact on delivery to customers.